Road work for the week of August 31
Posted Aug 31, 2020 10:00:00 AM.
A list of ongoing projects around the region can be found here.
Construction on the 401 and area highways can be followed here.
MONDAY AUGUST 31
Kitchener
Mt Hope Street partially closed at King Street West for Regional work
Monday, August 31 – Wednesday, September 30
Two-way traffic maintained; expect delays; pedestrian traffic maintained around work zone.
Prospect Avenue closed from Broadview Avenue to Franklin Street North for sewer work
Monday, August 31
One day closure local traffic only
Waterloo
Lanes reduced at Erb Street East and Goldbeck Street for utility work
Monday, August 31 – Wednesday, September 30
Two-way traffic maintained; pedestrian traffic maintained around work zone
Lanes reduced at University Avenue East and Lincoln Road for road reconstruction
Monday, August 31 – Friday, September 4
Two-way traffic maintained with flagging operation; expect delays; pedestrian traffic maintained around work zone.
Shakespeare Drive closed from Longfellow Drive to Mohawk Avenue for sewer repairs
Monday, August 31 – Tuesday, September 1
Road closed for sewer lateral repairs at 290 and 297 Shakespeare Drive – No through traffic – Local access only
TUESDAY SEPTEMBER 1
Kitchener
Courtland Avenue East partially closed from Siebert Avenue to Shelley Drive for water repair
Tuesday, September 1 – Saturday, October 10
Two-way traffic maintained; expect delays; pedestrian traffic maintained around work zone
Shirley Avenue closed at Wellington Street North for sewer work
One day closure access open to culdesac
Work at 12 Shirley Avenue
Waterloo
Lanes reduced at Erb Street West and Dietz Avenue South for manhole work
Tuesday, September 1
Two-way traffic maintained; expect delays; pedestrian traffic maintained around work zone.
Dick Street closed from Melbournce Crescent to Westmount Road South for site servicing
Tuesday, September 1 – Wednesday, September 2
Road closed for site servicing at 240 Dick St – No through traffic
WEDNESDAY SEPTEMBER 2
Kitchener
Fernwood Place closed at Westwood Drive for sewer work
Wednesday, September 2
One day closure
Waterloo
Lanes reduced at University Avenue East and Marland Drive for manhole work
Wednesday, September 2
Two-way traffic maintained; pedestrian traffic maintained around work zone
Avondale Avenue South Closed from Allen Street West to John Street West for sewer repairs
Wednesday, September 2
Road closed for sewer lateral repairs at 148 Avondale Avenue – No through traffic – Local access only, however expect some delays – Pedestrians will be directed around the work area
THURSDAY SEPTEMBER 3
Cambridge
Lanes reduced at Hespeler Road and Eagle Street North for Regional work
Thursday, September 3
Two-way traffic maintained; expect delays; pedestrian traffic maintained around work zone.
Kitchener
Wilson Avenue closed from Ninth Avenue to Woodhaven Road for sewer work
Thursday, September 3
One day closure local traffic only
Waterloo
Longwood Drive closed at Greenbrier Drive for sewer repairs
Thursday, September 3
Road closed for sewer lateral repairs at 111 Longwood Drive – No through traffic – Local access only, however expect some delays – Pedestrians will be directed around the work area.
Martindale Crescent closed at Dogwood Lane for sewer repairs
Thursday, September 3 – Friday, September 4
Road closed for water service repair in front of 301 Martindale Cres – No through traffic
Young Street East and Regina Street North closed for road reconstruction
Thursday, September 3
Intersection closed for road reconstruction – No through traffic
FRIDAY SEPTEMBER 4
SATURDAY SEPTEMBER 5
SUNDAY SEPTEMBER 6